Bidbacker / Guides
Template

Pre-bid RFI template, with real examples

A pre-bid request for information is the cheapest insurance a subcontractor has. One clear question before the deadline can turn a guess into an addendum that every bidder prices the same way.

BIDBACKER · UPDATED 25 NOVEMBER 2026 · 6 MIN READ

01When and where to send it

Send it in writing to the contact the instructions to bidders name, usually the architect or engineer, before the question deadline those instructions set. Answers that matter come back as an addendum to all plan holders, and only written addenda change the documents.

02The template

PRE-BID REQUEST FOR INFORMATION

Project:            [project name and owner's number]
Bid package:        [trade / division]
RFI no.:            [01]
Date:               [date]
To:                 [architect or engineer named in the instructions to bidders]
From:               [company, contact, email, phone]
Response needed by: [date, before the question deadline]

Reference
[Spec section and paragraph, sheet and note number, addendum item]

What the documents say
[Quote the exact words. If two documents disagree, quote both.]

Question
[One question, answerable with a yes, a no or a number.]

Why it matters to the bid
[What changes in scope, cost or schedule depending on the answer.]

Proposed answer
[The assumption we will price if the answer confirms it.]

03Six rules that get RFIs answered

  1. One question per RFI. Two questions in one letter get one answer.
  2. Cite the exact place. Section, paragraph, sheet, note. The engineer should not have to search.
  3. Quote, do not paraphrase. Quoting both sides of a conflict makes the problem obvious.
  4. Propose an answer. "Please confirm X" is answered faster than "please clarify".
  5. Send early. Late questions are often answered after the last addendum, or not at all.
  6. Plan for no answer. Some bid forms reject conditional bids, so an open question becomes a risk you price, not an exclusion you write.

04Four worked examples from a real bid

From our review of a closed public bid: replacement of UPS units in a university data center. All quotes are from the public bid documents.

RFI 01. Bid security thresholdReference: Invitation to Bid; Instructions to Bidders 7.2. The invitation asks for 10% security on bids "equal to or greater than $150,000"; the instructions say proposals "over $150,000". Question: is the threshold measured on the base bid or on base bid plus Alternate 1? Why it matters: a base bid under the line with an alternate that takes it over may or may not need security.
RFI 02. Missing remediation sectionReference: Section 024119, 1.7 D.1; table of contents. Section 024119 says hazardous material remediation "is specified elsewhere in the Contract Documents", but the manual has no remediation section. Question: is any asbestos removal in the base bid, and who performs it if the work disturbs the floor tile or wall texture?
RFI 03. Number of units removedReference: Sheet E1 scope of work; Section 011000 B.1. Sheet E1 describes demolition of five existing UPS units; Section 011000 describes replacement of two. Question: which units are removed in the base bid and which in Alternate 1, and is battery disposal ours for each?
RFI 04. Outage noticeReference: Supplemental Conditions 10.3.7; Section 011000 F.2; drawing general note A. The conditions ask for 72 hours notice; the drawings ask for two weeks. Proposed answer: two weeks governs, and outages fall in academic breaks.

See all nine RFIs in the full review →

05Questions

What if the RFI is not answered before bid day?

Check whether the bid form allows qualifications. Some public bid forms reject conditional bids outright, as the form in the example did, so the unanswered question becomes a risk you price rather than an exclusion you write.

Who should the pre-bid RFI go to?

To the person the instructions to bidders name, usually the architect or engineer, in writing. Oral answers are normally not binding; only written addenda change the documents.