Renne Library Data Center UPS Replacements
This is the review we would have sent an electrical contractor who forwarded this invitation. It is a real public bid, read from the public documents only. Every line points to the page it came from.
- Call
- Bid, if you are registered in Montana and have a UPS vendor who can commit to a delivery date before the summer outage window. Otherwise pass.
- Scope
- Remove old UPS units, install a new 45 kW UPS, re-feed the panels, rewire the emergency power off. Second UPS is the alternate.
- Addenda
- 1 issued, 18 Nov 2025. Adds EPO rewiring and halon control removal to the base bid. Outage notice becomes 2 weeks.
- Risks
- Outages only in academic breaks. Asbestos in the raised floor tile. No liquidated damages, but actual damages can be claimed.
- RFIs
- 9 drafted below. The bid security one was live: both bids crossed $150,000 only with the alternate.
01Dates that matter
| 12 Nov 2025, 10:00 | Pre-bid walk-through, Plew Building. "Attendance is strongly recommended." Invitation to Bid |
| 15 Nov 2025 | Last day for written questions and for substitution requests on Form 099: both at least 10 days before bid opening. ITB 5.1, 9.2 |
| 18 Nov 2025 | Addendum 1 issued. It must be acknowledged on the bid form. Addendum 1 |
| 25 Nov 2025, 14:00 | Sealed bids due, opened and read aloud at MSU University Facilities Management. Invitation to Bid |
| 30 days | Bids cannot be withdrawn after closing. ITB 8.2 |
| 15 days | To sign the contract after award, with insurance, bonds and registration, or the bid security is forfeited. ITB 7.4, 7.6 |
| 19 Aug 2026 | Substantial completion. ITB 17.1 |
02Scope for the electrical trade
- Base bid, phases 1 and 2. Demolish existing UPS units and their conductors. Install new UPS-A: 45 kW / 45 kVA, 15 minutes at full load, 120/208 V, 3-phase 4-wire, fed from the existing 225 A 3-pole breaker. New #4/0 feeders with #4 ground in 2-1/2" conduit, temporary feed during the changeover, panels BE3, BE3L, S2 and S2A re-fed. 263353 1.2; E4, E5
- Alternate 1, phase 3. New UPS-B, removal of UPS-S4 and the wall-mounted maintenance bypass. Panel Z feeders to UPS-B and on to panel S4. 012300 3.1; E6
- Added by Addendum 1. Wire both new UPS units and the existing HVAC units to the existing EPO buttons and contactor. Remove unused EPO wiring, old UPS and halon conduit and wire, and the halon control station. Update labels. Addendum 1, item 2a
- Equipment. Eaton is the basis of design; Eaton, APC or approved equal. Online double conversion with external maintenance bypass, 3-breaker sidecar bypass with shunt trip on the input breaker. 263353 2.1; E2 note C; Addendum 1, item 1a
- Install rules. Conduit under the raised floor in flexible metallic conduit; only the UPS-A feeder runs in EMT above the ceiling. No new holes in raised floor tiles: use MSU's spare pre-drilled tiles. E2 notes B and asbestos 3; Addendum 1, item 4c-iii
- Start-up and handover. Factory start-up per UPS, two separate start-ups if both are installed, operator training, one-year factory warranty. All removed UPS units are disposed of by the contractor, none returned to MSU. 263353 3.2, 3.3; Addendum 1, items 4c-ii, 4j
03What the bid must contain
- Bid form. Base bid and Alternate 1, each in words and figures, every blank filled, no conditions or erasures, Addendum 1 acknowledged with its date. ITB 6.8; Bid Proposal
- Bid security. 10% of the bid when it crosses $150,000. See RFI 04 on how the threshold is measured. ITB 7.2; Invitation to Bid
- Registration and signature. Montana construction contractor registration number on the form. Signed by a principal or an officer, or by an agent with a board resolution or power of attorney attached. Bid Proposal; ITB 6.9
- At award. 100% performance bond and 100% labor and material payment bond on contracts over $150,000. Buy Safe Montana form with incident rate, EMR and loss ratio. GC 11.7; ITB 16.1
- During the job. Montana prevailing wage rates. Subcontractors over $5,000 listed with pay applications. MSU may take up to 35 days to approve a pay request without owing interest. Project manual TOC; SC 9.3.7.2.3; ITB 15.1
04Risks to price
- Outage windows. Every outage needs 2 weeks notice and must fall in winter break, spring break or the summer session, unless UIT agrees otherwise. With both UPS units, there are two outages a couple of weeks apart and two factory start-ups, all before 19 August 2026. Price the UPS lead time against those windows, not against the completion date. E2 to E6 note A; Addendum 1, item 4c-i
- Actual damages. Liquidated damages are waived, but the owner keeps the right to actual damages for each day of delay. Delay claims must be made in writing within one week of the cause. ITB 17.2; SC 8.3.4
- Asbestos. The 12" vinyl floor tile on the raised floor panels and the sand swirl texture on the concrete walls contain asbestos. If suspect material is hit, work in that area stops until the owner decides. IH report, Appendix A; 260000 1.19 D
- Substitution cost. If a non-Eaton UPS needs different breakers in panel Z or BE1, the electrical contractor pays for them. E2 to E6 note C
- Discrepancies. Where drawings and specifications disagree, the contractor provides the greater quantity or quality at no extra cost. 011000 K
- Getting the equipment in. The data center is on the base level; the recommended route for heavy equipment is the north doors, and there are stairs there too. Each UPS component must be under 34.5" wide to pass a 3'-0" door. Price the rigging. Addendum 1, item 4e; 263353 1.2 A.2
- Live room rules. No dust in the data center, isolate or cover equipment. Tools only on non-UPS, non-generator panels agreed with UIT. EPO tests only under the engineer and MSU UIT, with the other UPS and HVAC units disconnected. Addendum 1, items 2a, 4g to 4i
05RFIs, ready to send
- Where is the hazardous material remediation specified?Section 024119 says remediation "is specified elsewhere in the Contract Documents", but the manual has no remediation section. Please confirm whether any asbestos removal is in the base bid, and who performs it if the work disturbs the floor tile or wall texture.024119 1.7 D.1; Table of Contents
- Is the wall behind the new UPS locations textured with asbestos-containing surfacing?Sheet E2 note 3 asks us to remove surface-mounted boxes and devices on that wall. The IH report finds asbestos in the sand swirl texture on concrete walls, and the asbestos notes forbid drilling textured walls. Please confirm the wall type and the procedure for removing those boxes.E2 note 3 and asbestos note 2; IH report
- How many existing UPS units are removed in the base bid?Sheet E1 describes demolition of five existing UPS units; Section 011000 describes replacement of two. Please list the units removed in the base bid and in Alternate 1, and confirm battery disposal is ours for each.E1 scope of work; 011000 B.1; Addendum 1, item 4j
- Is the $150,000 bid security threshold measured on the base bid or on base plus Alternate 1?The Invitation to Bid says bids "equal to or greater than $150,000" need 10% of the total bid; ITB 7.2 says proposals "over $150,000". A base bid under the threshold with an alternate that takes it over is unclear.Invitation to Bid; ITB 7.2
- Which APC features are accepted in place of Eaton-specific ones?Section 263353 names the Energy Saver System, Line-and-Match battery cabinets and PredictPulse monitoring, which are Eaton product names. Addendum 1 lists APC vendors but records no prior approvals. Please confirm an APC unit meeting the ratings is compliant without these named features.263353 1.2, 3.3 C; Addendum 1, items 3a and 5
- Does start-up by an authorized partner meet the field service rule?263353 1.5 D requires field engineers employed directly by the manufacturer and rejects third-party service. Addendum 1 lists Nationwide Power for Eaton and CFT for APC. Please confirm their start-up and warranty service are acceptable.263353 1.5 D; Addendum 1, item 3a
- Are the service office map and maintenance contract offers due with the bid?263353 1.5 D and G say both are submitted or offered "with the proposal", but the bid form has no place for them. Please confirm whether they are due on bid day or with submittals.263353 1.5 D, G; Bid Proposal
- Which outage notice governs, and what are the 2026 windows?Supplemental Conditions 10.3.7 and Section 011000 ask for 72 hours or 3 working days; the drawings and Addendum 1 ask for 2 weeks. Please confirm 2 weeks governs and give the 2026 spring break and summer session dates.SC 10.3.7; 011000 F.2; E2 note A; Addendum 1, item 4c-i
- Is there a freight route to the base level?The north doors are recommended for heavy equipment, but they also have stairs. Please confirm whether an elevator or ramp is available, and whether MSU expects the contractor to provide stair rigging for the UPS modules and battery cabinets.Addendum 1, item 4e
06What happened
Two contractors bid. Both acknowledged the addendum and included bid security. Both base bids were under $150,000, and both totals crossed it only with the alternate, which is why RFI 04 mattered.
bids received. 3 contractors signed in at the walk-through
low base bid. The other base bid was $121,461, 22% higher
low price for Alternate 1. The other was $107,926, 28% higher
Source: MSU bid results and the Addendum 1 sign-in sheet. Contractor names are public there; we leave them out here.